The framing of the walls is just about complete - notice, in the last picture, the circular sacred space taking shape on the fourth floor. Not quite as noticeable, but nonetheless a very important step between the layout of the walls and the application of the drywall, the electrical has been roughed in. Lastly, you can see a stairway now fills the hole that was cut between the third and fourth floors some time ago.

 
 
 